Project artifact · Risk and decisions

Risk and Decision Register

The controls that addressed data quality, adoption, continuity, and the risk of copying the old workflow without understanding it.

Prepared as a public, sanitized technical project-management artifact.
Risk principle: The old tables were treated as evidence to interpret, not as a complete description of the operating model.

Risk register

RiskPotential effectInitial response
Hidden workflow rulesImportant logic exists only in people’s habits or private workarounds.Map the process, use coexistence, and keep a decision log.
Data mismatchRecords do not map cleanly to the target model.Define schema mapping before migration and test representative sample data.
Team rejectionA generic admin screen does not fit the roles doing daily work.Build role-appropriate views and validate them with the team.
Incomplete handoffThe CRM depends on the person who originally built it.Provide SOPs, known-issues notes, and clear ownership.
Premature cutoverMissing scenarios or data gaps interrupt daily operations.Keep systems in parallel until selected scenarios are validated.

Key decisions

Schema before screens

Model the work and relationships before reproducing old views.

Coexistence before cutover

Use a parallel period to reveal missing states, data gaps, and ownership questions.

Scenario-based validation

Test the work the team actually needs to perform, not only technical setup.

Handoff as deliverable

Documentation and ownership are part of the system’s readiness.