Project Schedule

The PM maps the planning activities, dependencies and decision gates for the AegisShield Firewall.

AegisShield Web Application Firewall · Week 5 baseline

AegisShield, BookEasy, the people, findings and decisions are fictional and created for portfolio demonstration.

Baseline milestones

TimingMilestoneGate
Weeks 2–3Scope and requirementsProduct approval
Weeks 3–4Prototype and technical directionProduct and Security review
Week 5Backlog, capacity and schedule baselinePM and sponsor review
Weeks 6–7Safety controls and pilot preparationOperations and QA readiness
Week 8Pilot-build recommendationCTO decision

Critical dependencies

The engine assessment must inform the technical approach; the requirements and prototype must inform the backlog; and rule-safety, monitoring and rollback controls must be ready before any controlled pilot decision.