Back to case study

Project document - RFL-001

RACI and Backlog Refinement Meeting Notes

The meeting record used to review responsibilities, confirm backlog readiness, and assign the follow-up evidence needed before execution baseline approval.

ProjectCybersecurity Platform ModernizationMeeting typeRACI and backlog refinement
DateWeek 7 - fictional case studyFacilitatorJunior Technical Project Manager
Version / statusv0.1 - Complete meeting recordSourceWBS-001 / RACI-001 / BLG-001
PurposeReview responsibility assignments and backlog readiness before the Project Manager baselines the work for execution planning.

Participants and purpose

Participant / groupRole in meetingContribution expected
CTO / Project SponsorDecision authorityConfirms scope boundary, conditions, and escalation path
Junior Technical Project ManagerFacilitator and recorderCoordinates refinement, updates records, and tracks actions
Engineering LeadTechnical reviewerConfirms feasibility, dependencies, estimates, and implementation ownership
Security LeadSecurity reviewerConfirms controls, vulnerabilities, evidence, and risk treatment
DevOps / SRE LeadDelivery reviewerConfirms environments, deployment, monitoring, and rollback work
QA LeadQuality reviewerConfirms regression coverage and acceptance evidence
Product Manager / Customer Success LeadCustomer-impact reviewersConfirm critical workflows, timing, and customer constraints

RACI and Backlog Refinement Meeting Notes - continued

Review outcomes

The team reviewed the RACI against the baselined WBS and checked that the backlog items remain within the approved first-increment scope.

Review areaOutcomeRecord updatedResult
RACI reviewOne accountable role was confirmed for each WBS package; supporting technical and business roles remain visible.RACI-001 v0.2Reviewed
Backlog structureBacklog items were checked against the WBS and kept within the first-increment boundary.BLG-001Confirmed
OwnershipThe backlog owner fields identify the lead role; named individuals are assigned when team capacity is confirmed.BLG-001Open for baseline
Acceptance evidenceEach item has an expected outcome or acceptance condition linked to a deliverable or evidence record.BLG-001Confirmed
DependenciesDependencies were recorded where sequencing affects environment readiness, testing, security, or release.BLG-001Confirmed
EstimatesDetailed effort estimates remain subject to technical-owner confirmation after the evidence inventory is complete.BLG-001Action required

RACI and Backlog Refinement Meeting Notes - continued

Actions agreed

Action IDActionOwnerTimingStatus
BR-001Confirm deployed runtime and dependency evidence for BL-002 and BL-003.Engineering LeadBefore backlog baselineOpen
BR-002Confirm priority security findings and treatment path for BL-004.Security LeadBefore go/no-go planningOpen
BR-003Confirm non-production access, monitoring, and rollback prerequisites for BL-007.DevOps / SRE LeadBefore implementation schedulingOpen
BR-004Confirm critical-path regression coverage and acceptance evidence for BL-010.QA LeadBefore test planningOpen
BR-005Update the RACI and backlog records, then prepare the baseline review.Project ManagerAfter actions BR-001 to BR-004Open

Decision

The team agreed that the backlog is structurally ready for baseline review, but execution should not be scheduled until the technical evidence, capacity, and acceptance actions above are confirmed.

RACI and Backlog Refinement Meeting Notes - continued

Open questions

Question IDQuestionOwnerBacklog link
RQ-001Which deployed runtime, framework, and dependency versions are confirmed by production evidence?Engineering LeadBL-002 / BL-003
RQ-002What capacity and change window are available for the first non-production increment?Sponsor / Engineering / DevOpsBL-006 / BL-007
RQ-003Which customer workflows require explicit Customer Success sign-off before release?Product / Customer SuccessBL-005 / BL-012

Next step

The Project Manager will update RACI-001 to v0.2 and BLG-001 to v0.2 after the assigned actions are confirmed. The next governance point is the backlog baseline review, followed by release and sprint planning.