Work Breakdown Structure

A three-level breakdown of the AHI real-time marketing data and analytics application, with unique identifiers and an action → result statement for every activity.

Prepared as a public, sanitized portfolio artifact.
Public review note: The scenario is educational and sanitized. Names, dates, figures, identifiers, and other details have been changed or generalized for privacy and security.

Hierarchy

Level 1

The complete AHI App Development Project.

Level 2

Four project phases: Design, Development, Test, and Launch and Approve the App.

Level 3

Twenty-four work packages and activities, each linked to a measurable result.

Level 1 and Level 2 phases

CodeLevelPhaseDurationAction → result
1.0Level 1AHI App Development ProjectProject lifecycleDevelop and launch the AHI real-time marketing data application.
1.1Level 2Design30 daysDefine and approve the solution design.
1.2Level 2Development90 daysBuild and validate the application.
1.3Level 2Test30 daysVerify the app and prepare users for acceptance.
1.4Level 2Launch and Approve the App60 daysLaunch, monitor, improve, and close the project.

Level 3 work packages

CodePhase / activityDurationAction → result
1.1.1Requirements Definition8 daysDefine app requirements → approved requirements baseline.
1.1.2Vendor Identification4 daysIdentify qualified vendor → vendor shortlist.
1.1.3Vendor Contract3 daysFinalize vendor agreement → authorized delivery support.
1.1.4Initial Design8 daysDevelop initial design → reviewable solution design.
1.1.5Design Feedback and Updates5 daysGather feedback and update design → refined design.
1.1.6Final Design Approval2 daysObtain approval → authorized final design.
1.2.1Initial Prototype35 daysBuild prototype → demonstrable core application.
1.2.2IT Upgrades30 daysImplement hardware, software, storage, and security upgrades → ready environment.
1.2.3Launch Planning20 daysDevelop launch plan → approved release approach.
1.2.4Prototype Beta Testing20 daysPerform beta test → recorded test results.
1.2.5Beta Feedback and Updates20 daysGather beta feedback and update prototype → improved prototype.
1.2.6Prototype Sign-off15 daysObtain sign-off → approved prototype.
1.3.1Full-scale Development12 daysBegin full-scale development → completed release build.
1.3.2IT Hiring8 daysBegin IT hiring → qualified candidate pipeline.
1.3.3Final Prototype Testing8 daysTest final prototype → verified defects and results.
1.3.4Customer Acceptance4 daysObtain customer acceptance → accepted release.
1.3.5Launch Plan Approval3 daysApprove launch plan → authorized launch.
1.3.6Marketing Training3 daysTrain Marketing personnel → prepared users.
1.4.1New Hire Finalization10 daysFinalize new hires → confirmed staffing plan.
1.4.2Initial App Launch5 daysLaunch the app → available production release.
1.4.3Performance Monitoring15 daysMonitor app performance → operational metrics.
1.4.4Issue Documentation5 daysDocument app issues → assigned issue log.
1.4.5Upgrade Planning and Implementation15 daysPlan and implement upgrades → approved improvement release.
1.4.6Version 2 and Closeout10 daysPlan Version 2 and complete closeout → archived project and follow-up backlog.