Project Close-Out Report

A close-out record for the AHI app, covering goals, scope, schedule, cost, risk, outstanding work, lessons learned, and recommendations.

Report date: November 20xx · Core deliverable complete with follow-up ownership.
Public review note: The scenario is educational and sanitized. Names, dates, figures, identifiers, and other details have been changed or generalized for privacy and security.

Key information

ProjectAHI App Development Project
DepartmentMarketing and Technology
Baseline budget$250,000 fixed budget
Final reported cost$257,000 — $7,000 over baseline
Final statusCore deliverable complete; follow-up items remain under ownership.

Project goals from the charter

  1. Develop an application that gathers and analyzes real-time marketing data to help AHI understand target markets and make faster decisions.
  2. Deliver the core application within the planned schedule and launch window.
  3. Address approved scope, data, security, storage, and interface requirements for a usable release.
  4. Deliver the project within the approved fixed budget of $250,000.
  5. Improve IT staffing and delivery approach so AHI can support the application and future enhancements.

Goal success analysis

GoalResultAnalysis
Real-time marketing data appSuccessfulThe core application was delivered to support marketing data, market insight, customer information, and decision-making.
Planned schedule and launchPartial successIntegration, testing, and late requirements created schedule pressure; non-critical enhancements moved to Version 2.
Approved scope and technical requirementsPartial successCore functionality was completed, while hardware, interface, security, storage, and data-feed work required follow-up.
Stay within $250,000Not achievedFinal reported cost was $257,000, a $7,000 variance caused by omitted equipment and inflationary/implementation factors.
Improve staffing and delivery methodPartial successOne qualified candidate was hired for two vacancies; IT and HR continued the second hire and future Scrum improvements.

Scope, schedule, and cost review

Scope

The core app and primary marketing-data purpose were delivered. Non-critical reporting and enhancements moved to Version 2.

Schedule

Late scope clarification and interface/data work created pressure. Future plans need integration time, testing buffer, and earlier change decisions.

Cost

Baseline: $250,000 · Final: $257,000 · Variance: +$7,000.

Risk analysis

Risk / issueClose-out observationFuture treatment
IT recruiting capacityOnly one qualified candidate was hired for two approved vacancies.Start recruiting earlier and coordinate the onboarding plan with HR.
Incomplete requirementsLate requirements contributed to scope pressure and Version 2 deferrals.Use stakeholder workshops, signed acceptance criteria, and a change-control threshold.
Data-feed and interface compatibilityAdditional sources and interface needs required technical review and rework.Run technical discovery and data-quality tests before baseline approval.
Budget overrunThe project closed $7,000 above budget.Add contingency and validate equipment assumptions.

Outstanding items

ItemResolutionOwner
Version 2 enhancements and deferred reportingPrioritize the backlog, confirm business value, and schedule the next release.Product Owner / Marketing
Post-launch interface, data-feed, and performance refinementsComplete a production review, log defects, and close items through the support backlog.IT
Second IT hireRecruit and onboard the approved technician.IT / HR
Benefits and adoption measurementTrack usage, data quality, feedback, market insight, and progress toward ROI.Marketing

Lessons learned and recommendations